BCHS Refurbishment

We have been working with a team from the DfE and B&K on a project to refurbish our school. For some areas of the school it will be economically better to demolish buildings and rebuild with a new building. We are now entering the final phases of the planning of this exciting and school changing project and are hoping to move very quickly to the actual refurbishment and re building in 2021.

The video below gives an overview of the scheme but for further regular updates on our exciting refurbishment project please click here.

Please use the link below to visit our blog for the latest updates on the continuing building work at BCHS:

https://drichardsonbch.wixsite.com/my-site

 

PROPOSED BUILDING TIMELINE SCHEDULE 

 

July 2021   Contractor starts on site 

July 2021 – Sept 2021  Construct temporary road to side of field 

July 2021 –December 2021  Make all the trenches for the new Gas, Electric, water and fibre cable runs and drainage 

October 2021 – December 2021  Make new car park to the front of the school buildings 

December 2021 – November 2022  Building A on the rear tennis courts is built 

January 2022 – December 2022  Building B on the front car park is built 

December 2022 – January 2023  Move into both new buildings and use them from 09/01/2023 

January 2023 – July 2023  Old science block is demolished 

April 2023 – July 2023  Asbestos removal from old block EFAA – all staff and lesson no longer in there 

April 2023 – May 2024  EFAA refurbished 

July 2023 – March 2024 Sports hall block refurbished 

June 2024 – July 2024  Road removed from field 

July 2024  Project completed 