BCHS Refurbishment
We have been working with a team from the DfE and B&K on a project to refurbish our school. For some areas of the school it will be economically better to demolish buildings and rebuild with a new building. We are now entering the final phases of the planning of this exciting and school changing project and are hoping to move very quickly to the actual refurbishment and re building in 2021.
The video below gives an overview of the scheme but for further regular updates on our exciting refurbishment project please click here.
Please use the link below to visit our blog for the latest updates on the continuing building work at BCHS:
https://drichardsonbch.wixsite.com/my-site
PROPOSED BUILDING TIMELINE SCHEDULE
July 2021 Contractor starts on site
July 2021 – Sept 2021 Construct temporary road to side of field
July 2021 –December 2021 Make all the trenches for the new Gas, Electric, water and fibre cable runs and drainage
October 2021 – December 2021 Make new car park to the front of the school buildings
December 2021 – November 2022 Building A on the rear tennis courts is built
January 2022 – December 2022 Building B on the front car park is built
December 2022 – January 2023 Move into both new buildings and use them from 09/01/2023
January 2023 – July 2023 Old science block is demolished
April 2023 – July 2023 Asbestos removal from old block EFAA – all staff and lesson no longer in there
April 2023 – May 2024 EFAA refurbished
July 2023 – March 2024 Sports hall block refurbished
June 2024 – July 2024 Road removed from field
July 2024 Project completed